Facility Type
2-14 Connections
Inspection Type
Routine
Inspection Date
August 24, 2023
Number of critical violations
0
Number of non-critical violations
1
318
Non-Critical Inadequate Microbiological Analysis data
Corrective Actions: Shock chlorination of the water supply system is required to address the increased microbiological activity in the well since the new well pump was installed. Completion of this process is required no later than September 1, 2023 followed by the submission of two microbiological samples collected 24 - 48 hours apart. If these sample results are satisfactory, routine microbiological sampling can resume. Adverse results will necessitate further follow-up. Please contact this office to confirm the date of the scheduled well disinfection.